present: Sergey,  
present: Sergey, Cole, Volker, Rafo, Nick, Valery, Ben, Stepan, Latifa


* CLAS12 Trigger
* CLAS12 Trigger
Line 13: Line 13:


* 17 VTP boards connection (Ethernet, serial, fibers) - Chris Cuevas, Armen Stepanyan, Mark Taylor
* 17 VTP boards connection (Ethernet, serial, fibers) - Chris Cuevas, Armen Stepanyan, Mark Taylor
* fanout (SSP) for HTCC - Ben




Line 39: Line 41:


* validation 2 (GEMC vs C++ vs CLARA) - detector groups ? ( Cole, ..)
* validation 2 (GEMC vs C++ vs CLARA) - detector groups ? ( Cole, ..)
* geometrical match tables - Andrea




Line 45: Line 49:
* trigger config files, configuration manual - Ben, Sergey
* trigger config files, configuration manual - Ben, Sergey


* DAQ configuration procedures - Sergey
* DAQ configurations - Sergey, Ben




Line 55: Line 59:




6. Cosmic commissioning - Ben, Sergey, Cole, ...
6. Cosmic commissioning (with plan) - Ben, Sergey, Cole, ...




Line 63: Line 67:
'''Progress since last meeting:'''
'''Progress since last meeting:'''


* 12 VTP boards installed in Hall (Ben, Sergey): 10 in DC and 2 in FTOF sectors 5 and 6. Five more VTPs needs repair - in progress. Cabling under way, should be ready in few days (Vhris, Mark, Armen). All VTP installation may take couple of weeks because of needed repairs.
* 12 VTP boards installed in Hall (Ben, Sergey): 10 in DC and 2 in FTOF sectors 5 and 6. Five more VTPs needs repair - in progress. Cabling under way, should be mostly ready in few days, but new fiber trunk installation may take 2 weeks - not enough ports on SF (Chris, Mark, Armen). All VTP installation may take couple of weeks because of needed repairs.


* HTCC from GEMC is included into trigger validation (Rafo, Sergey), we have now PCAL, ECAL and HTCC, FT (Andrea) and FTOF(Sergey) are in progress.
* HTCC from GEMC is included into trigger validation (Rafo, Sergey), we have now PCAL, ECAL and HTCC, FT (Andrea) and FTOF(Sergey) are in progress.
* Andrea sent first version of FTOF-PCAL geometry table, PCAL-ECAL to go
'''Ben's presentation on trigger stage2/3'''
[https://clonwiki0.jlab.org/wiki/clondocs/CLAS12_Stage_2_Trigger_Summary.pdf stage 2 timing diagram and FT/HODO]
'''to do'''
* monitoring screens - epics_server-URGENT
* GUI - Valery will provide layout
* evio banks decoding - Gagik, Andrey Kim
* beam commissioning plan - Valery
* next week turn everything installed on
* HTCC trigger will be modified: 36bit mask -> 48bit mask

Latest revision as of 10:33, 18 October 2017

present: Sergey, Cole, Volker, Rafo, Nick, Valery, Ben, Stepan, Latifa

  • CLAS12 Trigger


Remaining work in CLAS12 trigger system before Dec 4, 2017 run

1. Hadrware:

  • 17 VTP boards assembly and testing - Ben Raydo, Jeff Wilson
  • 17 VTP boards installation (10-DC, 6-FTOF, 1-CND) - Ben Raydo, Sergey Boyarinov
  • 17 VTP boards connection (Ethernet, serial, fibers) - Chris Cuevas, Armen Stepanyan, Mark Taylor
  • fanout (SSP) for HTCC - Ben


2. Firmware:

  • ECAL: change from inner to total in cluster search - Sergey, Ben
  • FT - Ben
  • FTOF - Sergey, Ben
  • stage2, stage 3 - Ben


3. Simulation:

  • GEMC fadc mode1 digitization - Rafo
  • stage 1 (except FT) - Sergey
  • stage 1 (FT) - Andrea
  • stage2, stage 3 - Rafo
  • validation 1 (cosmic vs C++) - Sergey, Rafo
  • validation 2 (GEMC vs C++ vs CLARA) - detector groups ? ( Cole, ..)
  • geometrical match tables - Andrea


4. Configuration:

  • trigger config files, configuration manual - Ben, Sergey
  • DAQ configurations - Sergey, Ben


5. Monitoring:

  • trigger results in data stream - Sergey
  • histogramming, messaging, EPICS - ?


6. Cosmic commissioning (with plan) - Ben, Sergey, Cole, ...


7. Beam commissioning plan (starting configuration, parameters to be changed etc) - Valery, ...


Progress since last meeting:

  • 12 VTP boards installed in Hall (Ben, Sergey): 10 in DC and 2 in FTOF sectors 5 and 6. Five more VTPs needs repair - in progress. Cabling under way, should be mostly ready in few days, but new fiber trunk installation may take 2 weeks - not enough ports on SF (Chris, Mark, Armen). All VTP installation may take couple of weeks because of needed repairs.
  • HTCC from GEMC is included into trigger validation (Rafo, Sergey), we have now PCAL, ECAL and HTCC, FT (Andrea) and FTOF(Sergey) are in progress.
  • Andrea sent first version of FTOF-PCAL geometry table, PCAL-ECAL to go

Ben's presentation on trigger stage2/3

stage 2 timing diagram and FT/HODO

to do

  • monitoring screens - epics_server-URGENT
  • GUI - Valery will provide layout
  • evio banks decoding - Gagik, Andrey Kim
  • beam commissioning plan - Valery
  • next week turn everything installed on
  • HTCC trigger will be modified: 36bit mask -> 48bit mask