Created page with "present: Sergey * CLAS12 Trigger Remaining work in CLAS12 trigger system before Dec 4, 2017 run ============================================================== 1. Hadrware:..." |
No edit summary |
||
(10 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
present: Sergey | present: Sergey, Cole, Volker, Rafo, Nick, Valery, Ben, Stepan, Latifa | ||
* CLAS12 Trigger | * CLAS12 Trigger | ||
Remaining work in CLAS12 trigger system before Dec 4, 2017 run | '''Remaining work in CLAS12 trigger system before Dec 4, 2017 run''' | ||
1. Hadrware: | 1. Hadrware: | ||
Line 14: | Line 13: | ||
* 17 VTP boards connection (Ethernet, serial, fibers) - Chris Cuevas, Armen Stepanyan, Mark Taylor | * 17 VTP boards connection (Ethernet, serial, fibers) - Chris Cuevas, Armen Stepanyan, Mark Taylor | ||
* fanout (SSP) for HTCC - Ben | |||
Line 40: | Line 41: | ||
* validation 2 (GEMC vs C++ vs CLARA) - detector groups ? ( Cole, ..) | * validation 2 (GEMC vs C++ vs CLARA) - detector groups ? ( Cole, ..) | ||
* geometrical match tables - Andrea | |||
Line 46: | Line 49: | ||
* trigger config files, configuration manual - Ben, Sergey | * trigger config files, configuration manual - Ben, Sergey | ||
* DAQ configurations - Sergey | * DAQ configurations - Sergey, Ben | ||
Line 56: | Line 59: | ||
6. Cosmic commissioning - Ben, Sergey, Cole, ... | 6. Cosmic commissioning (with plan) - Ben, Sergey, Cole, ... | ||
7. Beam commissioning plan (starting configuration, parameters to be changed etc) - Valery, ... | 7. Beam commissioning plan (starting configuration, parameters to be changed etc) - Valery, ... | ||
'''Progress since last meeting:''' | |||
* 12 VTP boards installed in Hall (Ben, Sergey): 10 in DC and 2 in FTOF sectors 5 and 6. Five more VTPs needs repair - in progress. Cabling under way, should be mostly ready in few days, but new fiber trunk installation may take 2 weeks - not enough ports on SF (Chris, Mark, Armen). All VTP installation may take couple of weeks because of needed repairs. | |||
* HTCC from GEMC is included into trigger validation (Rafo, Sergey), we have now PCAL, ECAL and HTCC, FT (Andrea) and FTOF(Sergey) are in progress. | |||
* Andrea sent first version of FTOF-PCAL geometry table, PCAL-ECAL to go | |||
'''Ben's presentation on trigger stage2/3''' | |||
[https://clonwiki0.jlab.org/wiki/clondocs/CLAS12_Stage_2_Trigger_Summary.pdf stage 2 timing diagram and FT/HODO] | |||
'''to do''' | |||
* monitoring screens - epics_server-URGENT | |||
* GUI - Valery will provide layout | |||
* evio banks decoding - Gagik, Andrey Kim | |||
* beam commissioning plan - Valery | |||
* next week turn everything installed on | |||
* HTCC trigger will be modified: 36bit mask -> 48bit mask |
Latest revision as of 10:33, 18 October 2017
present: Sergey, Cole, Volker, Rafo, Nick, Valery, Ben, Stepan, Latifa
- CLAS12 Trigger
Remaining work in CLAS12 trigger system before Dec 4, 2017 run
1. Hadrware:
- 17 VTP boards assembly and testing - Ben Raydo, Jeff Wilson
- 17 VTP boards installation (10-DC, 6-FTOF, 1-CND) - Ben Raydo, Sergey Boyarinov
- 17 VTP boards connection (Ethernet, serial, fibers) - Chris Cuevas, Armen Stepanyan, Mark Taylor
- fanout (SSP) for HTCC - Ben
2. Firmware:
- ECAL: change from inner to total in cluster search - Sergey, Ben
- FT - Ben
- FTOF - Sergey, Ben
- stage2, stage 3 - Ben
3. Simulation:
- GEMC fadc mode1 digitization - Rafo
- stage 1 (except FT) - Sergey
- stage 1 (FT) - Andrea
- stage2, stage 3 - Rafo
- validation 1 (cosmic vs C++) - Sergey, Rafo
- validation 2 (GEMC vs C++ vs CLARA) - detector groups ? ( Cole, ..)
- geometrical match tables - Andrea
4. Configuration:
- trigger config files, configuration manual - Ben, Sergey
- DAQ configurations - Sergey, Ben
5. Monitoring:
- trigger results in data stream - Sergey
- histogramming, messaging, EPICS - ?
6. Cosmic commissioning (with plan) - Ben, Sergey, Cole, ...
7. Beam commissioning plan (starting configuration, parameters to be changed etc) - Valery, ...
Progress since last meeting:
- 12 VTP boards installed in Hall (Ben, Sergey): 10 in DC and 2 in FTOF sectors 5 and 6. Five more VTPs needs repair - in progress. Cabling under way, should be mostly ready in few days, but new fiber trunk installation may take 2 weeks - not enough ports on SF (Chris, Mark, Armen). All VTP installation may take couple of weeks because of needed repairs.
- HTCC from GEMC is included into trigger validation (Rafo, Sergey), we have now PCAL, ECAL and HTCC, FT (Andrea) and FTOF(Sergey) are in progress.
- Andrea sent first version of FTOF-PCAL geometry table, PCAL-ECAL to go
Ben's presentation on trigger stage2/3
stage 2 timing diagram and FT/HODO
to do
- monitoring screens - epics_server-URGENT
- GUI - Valery will provide layout
- evio banks decoding - Gagik, Andrey Kim
- beam commissioning plan - Valery
- next week turn everything installed on
- HTCC trigger will be modified: 36bit mask -> 48bit mask