September 5, 2012 online meeting minutes

From CLONWiki
Jump to navigation Jump to search

present: Sergey B, Sergey P, Eugene Pasyuk

FC almost ready for installation, need to remove remaining cables and Cherenkov gas control. Waiting for UPSes power in the hall. CC is programming bethsw1 switch to be installed on Pie Tower where HV test setup will be operating. In-hall fiber wiring will be ordered - FC only. SF will be done when all racks are in place including level 3/4. Have to install racks on FC level 1 before running fiber. Power to new racks to be ordered. 2 new racks are needed on upper level (cutting/welding required). Railings and stems must be installed on level 1. Maybe air conditioning is needed for level1 racks.

In counting house lock in drawer still need to be opened. Few crates and HV loads will be moved to the hall.