November 16, 2011 online meeting minutes

From CLONWiki
Jump to navigation Jump to search

present: Sergey Boyarinov, Sergey Pozdnyakov, Nerses, Eugene Pasyuk, Hovanes

g14b starts in a couple of days. EC and TOF calibration runs were completed, will need to repeat after some repaires. DC test was done, one ADB crate replaced, will repeat. tage and tage2 crates to be tested (intel cpus ?). Level2 to be checked, along with full trigger check. Helicity must be checked. Mysql part of run_log_begin need to be modified, mysql tables to be changed (Eugene). Fast reconstruction - check (tage need new calibration because of new tdcs). ST wired, need check.

halld test setup: halldtrg3 ready, clonusr2 ready but need to mount sfs61 and fix possible software problems, will make sudoer for halldrun user.

Forward tagger test: 13 dec italians will be here, then will install everything.

HPS: still installing racks and crates ...