April 24, 2019 online meeting minutes

From CLONWiki
Jump to navigation Jump to search

present: Sergey Boyarinov, Stepan Stepanyan, Graham, vpk, Rafo, Nathan, Ben


1. HallB cosmic runs organization: svt test setup can work now with and without ts, all wiring is done, Yuri will check data consistency; in general we can run our major sets in parallel


2. HPS preparations

  • DAQ status: cleanup, new release will be made; daq is running in the hall with 3 vie crates and 2 servers, everything is ready, waiting for ECAL and SVT
  • TIpcie board integration with SVT: test setup in SLAC is operational, SVT electronics being prepared there, some issues still exist, in particular phase synchronization have to be worked out
  • trigger status: by the end of week Ben will finish trigger simulation and will be ready for commissioning; all triggers presented in January in SLAC will be implemented, actual production and calibration triggers will be discussed
  • installation and commissioning plans: ECAL will be on Monday April 29, 2 scintillators are ready and will be installed as well, then trigger tests can be started; we have to finish in one week before SVT arrives May 6; if trigger delayed SD outputs can be used; SVT installation and testing will take about 10 days
  • HPS run starts Monday June 17; MCC starts June 10 so we may be ready few days before just in case; will go until August 18
  • Nathan will look at HPS slow control if it can/should be merged with CLAS
  • utility power will be added in alcove