October 17, 2012 online meeting minutes
present: Sergey Boyarinov, Sergey Pozdnyakov
1. CLAS12 construction:
- 2 racks were moved to the Hall from EEL by us, waining to be lifted to the FC level 3; support on level 3 was relocated but not attached to the floor yet, it can be done after racks are installed and connected to the adjacent ones
- 4 crates were installed on Pie Tower level 2: vmetest0, vxstest0, ioctest0 and ioctest1; first 2 will be used as DAQ test setup, and last 2 as slow control test setup; ioctest1 will represent old ioc (epics3.13) where old drivers will be learned, and ioctest0 with mvme6100 and epics3.14 will be used as a testbed for old drivers re-writing and new drivers commissioning; Johann Goetz started to work with VS4 step motor control driver with Krister Bruhwel
- still waiting for electrical to be done for UPSes and FC level 1, as well as for ethernet fibers by shields - will remind them
- support needed for HV patch panels was ordered (vertical installation)
- will restore a floor on FC level 2, decide on HV cables layout and start HV mainframes installation
- will bring parts for new racks from the storage bldg and start assembly
- after the meeting with manufacturer 2 set of labels will be ordered after new quota will be sent to us