present: Sergey Boyarinov, Sergey Pozdnyakov

1. g14b: run started week ago, following problems were fixed:

  • level2 cables connected under the CLAS
  • several above-FASTBUS fans replaced, will continue
  • several CPUs replaced because of PMC failures
  • rate was 4 kHz at 85% livetime at 20nA beam current BEFORE level2 fixes, expecting improvements
  • remaining problems