September 23, 2009 online meeting minutes

From CLONWiki
Revision as of 09:48, 23 September 2009 by 129.57.80.194 (talk)
Jump to navigation Jump to search

present: Sergey Boyarinov, Sergey Pozdnyakov, Stepan Stepanyan

1. Next run preparations:

  • BONUS readout: 3 PCs with Linux, 3 TI PCI cards, 3 RORCs, 6 crates, 26 FEC cards; new PCs will be installed on North SF, probably in DCHV rack on the floor; they will be connected to the branch instead of tage, tage2 and tage3; need 2 new TI PCI cards, and a lot of electronics still coming from Italy, and 3 DELL PCs still to be delivered; software for CODA readout was adjusted by Sergey B. from CERN test program, some issues still to be fixed (we are loading firmware in every prestart to make it work); we are testing BONUS in ELL building until Sep 28, then it will be moved to the Hall
  • it will be external trigger for BONUS, need to find empty TS input, maybe instead of TOF, probably 2 signals
  • hodoscope will be installed, electronics/readout is still there
  • Friday Oct 2 everything must be ready for the beam
  • need to improve helicity correction
  • fix sc2 crashes if possible (new coda_roc)


2.