CLAS12 Online System

From CLONWiki
Revision as of 15:02, 19 February 2009 by 129.57.76.91 (talk) (→‎Work in Counting Room)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Disassembling schedule in the Hall

  • Network wiring securing/removal, protecting/relocation of the fiber uplinks - 6 mandays
  • Unused equipment removal - 10 mandays

Assembling schedule in the Hall

  • Removal of the remaining cables on FC - 20 mandays
  • New racks installation (two 7ft racks on FC level2, ten 6ft racks on FC level 0) - ?? mandays
  • Patch panels (PMT Signals, High Voltage, Network etc) installation/relocation in racks - 10 mandays
  • Crates (High Voltage, VME, VME64X, VXS, NIM, CAMAC, ADB, FASTBUS etc) installation/relocation in racks - 60 mandays
  • Network equipment (Switches, Terminal Servers etc) installation in racks - 10 mandays
  • Signal/Network patch panels wiring - contractors job, can be done in 5 calendar days
  • Boards (ADC, TDC, High Voltage etc) installation/relocation in crates - 30 mandays
  • Boards cabeling and Network wiring - 30 mandays
  • Computers replacing/installation - 10 mandays
  • Preliminary testing/fixing of assembled electronics - 20 mandays

Work in Counting Room

  • Replacing old equipment (any convenient time, must be completed just before first run starts) - 60 mandays