October 3, 2007 online meeting minutes

From CLONWiki
Revision as of 08:51, 3 October 2007 by Boiarino (talk | contribs)
Jump to navigation Jump to search

DVCS Trigger System


Projects


  • PCAL


  • Wolfram


  • Lecroy repairs, sy527 AC connectors replacement
  • PrPMC880 replacement
  • Frost preparations: all power turned on including DC FASTBUS crates, ethernet/serial cables ran for target platform;

Carl still working on ET modifications, tests to be started dayli, new version expected in about a week, we'll wait, do modifications and then run full CLAS DAQ test

TODO:

  • sy527 support (similar to sy1527 but in VME crate because of VME CAENAT board v288)
  • v1190/v1290 extensive testing (CBLT, slot#, install mv6100 in the hall and switch to 2eSST)
  • DVCS Trigger Development
  • Hall B electronics inventarization
  • Upcoming run preparations on requests (fix flip-related problem in online delay reporting correction procedure, ..)