CLAS12 Online System
Disassembling schedule in the Hall
- Network wiring securing/removal, protecting fiber uplinks
- Unused equipment removal
Assembling schedule in the Hall
- Removal of the remaining cables on FC - 10 mandays
- New racks installation (2 7ft racks on FC level2, 10 6ft racks on FC level 0) - ?? mandays
- Patch panels (PMT Signals, High Voltage, Network etc) installation/relocation in racks - 2 mandays
- Crates (High Voltage, VME, VME64X, VXS, NIM, CAMAC, ADB, FASTBUS etc) installation/relocation in racks - 60 mandays
- Network equipment (Switches, Terminal Servers etc) installation in racks - 10 mandays
- Boards (ADC, TDC, High Voltage etc) installation/relocation in crates - 30 mandays
- Network wiring (interlinks by purchased cables, uplinks by contractors if necessary) - 15 mandays
- Preliminary testing/fixing of assembled electronics - 20 mandays
Work in Counting Room
- Replacing old equipment in convenient time, must be completed just before first run starts