CLAS12 Online System

From CLONWiki
Revision as of 14:13, 19 February 2009 by 129.57.76.91 (talk)
Jump to navigation Jump to search

Disassembling schedule in the Hall

  • Network wiring securing/removal, protecting fiber uplinks
  • Unused equipment removal

Assembling schedule in the Hall

  • Removal of the remaining cables on FC
  • New racks installation (2 7ft racks on FC level2, 10 6ft racks on FC level 0)
  • Patch panels (PMT Signals, High Voltage, Network etc) installation/relocation in racks
  • Crates (High Voltage, VME, VME64X, VXS, NIM, CAMAC, ADB, FASTBUS etc) installation/relocation in racks
  • Network equipment (Switches, Terminal Servers etc) installation in racks
  • Boards (ADC, TDC, High Voltage etc) installation/relocation in crates
  • Network wiring (interlinks by purchased cables, uplinks by contractors if necessary)

Work in Counting Room

  • Replacing old equipment in convenient time, must be completed just before first run starts