Created page with "present: Sergey * CLAS12 Trigger Remaining work in CLAS12 trigger system before Dec 4, 2017 run ============================================================== 1. Hadrware:..." |
No edit summary |
||
Line 1: | Line 1: | ||
present: Sergey | present: Sergey, | ||
* CLAS12 Trigger | * CLAS12 Trigger | ||
Remaining work in CLAS12 trigger system before Dec 4, 2017 run | '''Remaining work in CLAS12 trigger system before Dec 4, 2017 run''' | ||
1. Hadrware: | 1. Hadrware: | ||
Line 60: | Line 59: | ||
7. Beam commissioning plan (starting configuration, parameters to be changed etc) - Valery, ... | 7. Beam commissioning plan (starting configuration, parameters to be changed etc) - Valery, ... | ||
'''Progress since last meeting:''' | |||
* 12 VTP boards installed in Hall (Ben, Sergey): 10 in DC and 2 in FTOF sectors 5 and 6. Five more VTPs needs repair - in progress. Cabling under way, should be ready in few days (Vhris, Mark, Armen). All VTP installation may take couple of weeks because of needed repairs. | |||
* HTCC from GEMC is included into trigger validation (Rafo, Sergey), we have now PCAL, ECAL and HTCC, FT (Andrea) and FTOF(Sergey) are in progress. |
Revision as of 06:34, 18 October 2017
present: Sergey,
- CLAS12 Trigger
Remaining work in CLAS12 trigger system before Dec 4, 2017 run
1. Hadrware:
- 17 VTP boards assembly and testing - Ben Raydo, Jeff Wilson
- 17 VTP boards installation (10-DC, 6-FTOF, 1-CND) - Ben Raydo, Sergey Boyarinov
- 17 VTP boards connection (Ethernet, serial, fibers) - Chris Cuevas, Armen Stepanyan, Mark Taylor
2. Firmware:
- ECAL: change from inner to total in cluster search - Sergey, Ben
- FT - Ben
- FTOF - Sergey, Ben
- stage2, stage 3 - Ben
3. Simulation:
- GEMC fadc mode1 digitization - Rafo
- stage 1 (except FT) - Sergey
- stage 1 (FT) - Andrea
- stage2, stage 3 - Rafo
- validation 1 (cosmic vs C++) - Sergey, Rafo
- validation 2 (GEMC vs C++ vs CLARA) - detector groups ? ( Cole, ..)
4. Configuration:
- trigger config files, configuration manual - Ben, Sergey
- DAQ configurations - Sergey
5. Monitoring:
- trigger results in data stream - Sergey
- histogramming, messaging, EPICS - ?
6. Cosmic commissioning - Ben, Sergey, Cole, ...
7. Beam commissioning plan (starting configuration, parameters to be changed etc) - Valery, ...
Progress since last meeting:
- 12 VTP boards installed in Hall (Ben, Sergey): 10 in DC and 2 in FTOF sectors 5 and 6. Five more VTPs needs repair - in progress. Cabling under way, should be ready in few days (Vhris, Mark, Armen). All VTP installation may take couple of weeks because of needed repairs.
- HTCC from GEMC is included into trigger validation (Rafo, Sergey), we have now PCAL, ECAL and HTCC, FT (Andrea) and FTOF(Sergey) are in progress.