September 19, 2012 online meeting minutes: Difference between revisions
No edit summary |
No edit summary |
||
Line 1: | Line 1: | ||
present: Sergey Boyarinov, Sergey Pozdnyakov, FX, Elliott, Hovanes, Somov | present: Sergey Boyarinov, Sergey Pozdnyakov, FX, Elliott, Hovanes, Somov | ||
1. Inventory: Sergey B. reported progress on cables/connectors | 1. Inventory: Sergey B. reported progress on cables/connectors implementation; connectors need number and description to identify them inside every board or cable; need buttons to 'create' and 'delete' connectors, as well as 'recommended connecors' (means if cable type is picked, it suggest appropriate list of connectors - unmodifable with different color ?); add cable search; make 3 lines in main menu (items, cables, the rest) | ||
2. HV system: Hall D (Nerses) will finish epics driver for CAEN SY1527, we'll use it then; we received almost all HV equipment, except 1 mainframe, 1 extra suply for mainframe and some patch panels (will count); Hall D has MPOD epics drivers, had some problems with device dissapearing from network; all GUIs will be on CSS (Nerses again) | 2. HV system: Hall D (Nerses) will finish epics driver for CAEN SY1527, we'll use it then; we received almost all HV equipment, except 1 mainframe, 1 extra suply for mainframe and some patch panels (will count); Hall D has MPOD epics drivers, had some problems with device dissapearing from network; all GUIs will be on CSS (Nerses again) | ||
3. CLAS12 construction: will proceed with electronics installation as planed, no schedule change; HV testing will be over in 2 weeks, then installation will start; will push power installation; FX will work on DAQ/EPICS electronics list for beamline | 3. CLAS12 construction: will proceed with electronics installation as planed, no schedule change; HV testing will be over in 2 weeks, then installation will start; will push power installation; FX will work on DAQ/EPICS electronics list for beamline |
Revision as of 13:22, 19 September 2012
present: Sergey Boyarinov, Sergey Pozdnyakov, FX, Elliott, Hovanes, Somov
1. Inventory: Sergey B. reported progress on cables/connectors implementation; connectors need number and description to identify them inside every board or cable; need buttons to 'create' and 'delete' connectors, as well as 'recommended connecors' (means if cable type is picked, it suggest appropriate list of connectors - unmodifable with different color ?); add cable search; make 3 lines in main menu (items, cables, the rest)
2. HV system: Hall D (Nerses) will finish epics driver for CAEN SY1527, we'll use it then; we received almost all HV equipment, except 1 mainframe, 1 extra suply for mainframe and some patch panels (will count); Hall D has MPOD epics drivers, had some problems with device dissapearing from network; all GUIs will be on CSS (Nerses again)
3. CLAS12 construction: will proceed with electronics installation as planed, no schedule change; HV testing will be over in 2 weeks, then installation will start; will push power installation; FX will work on DAQ/EPICS electronics list for beamline