present: Sergey Boyarinov, Sergey Pozdnyakov, FX, Elliott, Hovanes
present: Sergey Boyarinov, Sergey Pozdnyakov, FX, Elliott, Hovanes, Somov


1. Inventory: Sergey B. reported progress on cables/connectors omplementation; connectors need number and description to identify them inside every board or cable; need buttons to 'create' and 'delete' connectors, as well as 'recommended connecors';  
1. Inventory: Sergey B. reported progress on cables/connectors omplementation; connectors need number and description to identify them inside every board or cable; need buttons to 'create' and 'delete' connectors, as well as 'recommended connecors' (means if cable type is picked, it suggest appropriate list of connectors - unmodifable with different color ?); add cable search; make 3 lines in main menu (items, cables, the rest)


2. HV system
2. HV system: Hall D (Nerses) will finish epics driver for CAEN SY1527, we'll use it then; we received almost all HV equipment, except 1 mainframe, 1 extra suply for mainframe and some patch panels (will count); Hall D has MPOD epics drivers, had some problems with device dissapearing from network; all GUIs will be on CSS (Nerses again)


3. CLAS12 construction
3. CLAS12 construction: will proceed with electronics installation as planed, no schedule change; HV testing will be over in 2 weeks, then installation will start; will push power installation; FX will work on DAQ/EPICS electronics list for beamline

Revision as of 10:40, 19 September 2012

present: Sergey Boyarinov, Sergey Pozdnyakov, FX, Elliott, Hovanes, Somov

1. Inventory: Sergey B. reported progress on cables/connectors omplementation; connectors need number and description to identify them inside every board or cable; need buttons to 'create' and 'delete' connectors, as well as 'recommended connecors' (means if cable type is picked, it suggest appropriate list of connectors - unmodifable with different color ?); add cable search; make 3 lines in main menu (items, cables, the rest)

2. HV system: Hall D (Nerses) will finish epics driver for CAEN SY1527, we'll use it then; we received almost all HV equipment, except 1 mainframe, 1 extra suply for mainframe and some patch panels (will count); Hall D has MPOD epics drivers, had some problems with device dissapearing from network; all GUIs will be on CSS (Nerses again)

3. CLAS12 construction: will proceed with electronics installation as planed, no schedule change; HV testing will be over in 2 weeks, then installation will start; will push power installation; FX will work on DAQ/EPICS electronics list for beamline