present: Sergey Boyarinov, Sergey Pozdnyakov, Eugene Pasyuk, FX, Nerses, Hovanes | present: Sergey Boyarinov, Sergey Pozdnyakov, Eugene Pasyuk, FX, Nerses, Hovanes | ||
1. Cables in inventory database: | 1. Cables in inventory database: Eugene presented the idea how to implement connections and cables into inventory database; after discussion following database tables were proposed: | ||
- | |||
connection | |||
id pin1_id pin2_id | |||
- | |||
pin | |||
id connector_id local_pin_id? | |||
- | |||
connector | |||
id type Npins host_id | |||
- | |||
cable | |||
id s/n type locical_name(label_on_cable) | |||
- | |||
board (exist) | |||
id s/n type ... | |||
2. Electronics testing: FADC will be moved to the Hall for testing with real detectors; v1190/v1290 testing is under way | 2. Electronics testing: FADC will be moved to the Hall for testing with real detectors; v1190/v1290 testing is under way | ||
3. Drift Chamber cosmic test and upcoming run preparations: cables on the floor were repaired, DC1 was fixed, may need to repair FASTBUS WIENER power supply, ready to run DAQ | 3. Drift Chamber cosmic test and upcoming run preparations: cables on the floor were repaired, DC1 was fixed, may need to repair FASTBUS WIENER power supply, ready to run DAQ |
Revision as of 09:50, 6 October 2011
present: Sergey Boyarinov, Sergey Pozdnyakov, Eugene Pasyuk, FX, Nerses, Hovanes
1. Cables in inventory database: Eugene presented the idea how to implement connections and cables into inventory database; after discussion following database tables were proposed:
- connection id pin1_id pin2_id - pin id connector_id local_pin_id? - connector id type Npins host_id - cable id s/n type locical_name(label_on_cable) - board (exist) id s/n type ...
2. Electronics testing: FADC will be moved to the Hall for testing with real detectors; v1190/v1290 testing is under way
3. Drift Chamber cosmic test and upcoming run preparations: cables on the floor were repaired, DC1 was fixed, may need to repair FASTBUS WIENER power supply, ready to run DAQ