present: Sergey Boyarinov, Sergey Pozdnyakov, Chris Cuevas, Eugene Pasyuk, McMollen, eng, Latifa | present: Sergey Boyarinov, Sergey Pozdnyakov, Chris Cuevas, Eugene Pasyuk, McMollen, eng, Latifa, Ben Raydo, Glen, Nerses | ||
1. SVT: VME or so readout board not covered, have to find group to design and produce it; will have a phone meeting with FNAL asap (Kwan) | |||
2. TPE preparations | |||
* LAC TDCs/DISCR wired back | |||
* new TDCs and DISCR installed to EC4 and wired - for TPE cal and DFM | |||
* need scalers: Sergey P. daq ones, nerses epics ones | |||
* need HV | |||
* fastbus TAGE was removed, VME installed, need to check flat cables and cleanup everything; trans table must be changed | |||
* DC cosmic test needed - for Dc and level2 control check | |||
* level1 to be completed and test |
Latest revision as of 11:08, 17 November 2010
present: Sergey Boyarinov, Sergey Pozdnyakov, Chris Cuevas, Eugene Pasyuk, McMollen, eng, Latifa, Ben Raydo, Glen, Nerses
1. SVT: VME or so readout board not covered, have to find group to design and produce it; will have a phone meeting with FNAL asap (Kwan)
2. TPE preparations
- LAC TDCs/DISCR wired back
- new TDCs and DISCR installed to EC4 and wired - for TPE cal and DFM
- need scalers: Sergey P. daq ones, nerses epics ones
- need HV
- fastbus TAGE was removed, VME installed, need to check flat cables and cleanup everything; trans table must be changed
- DC cosmic test needed - for Dc and level2 control check
- level1 to be completed and test