July 1, 2009 online meeting minutes: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
No edit summary |
||
Line 3: | Line 3: | ||
1.СLAS12 trigger: following equipment needed for the CLAS12 trigger system: | 1.СLAS12 trigger: following equipment needed for the CLAS12 trigger system: | ||
* CTP (Crate Trigger Processor): 19+1 | * CTP (Crate Trigger Processor): 19+1 | ||
* TI (Trigger Interface): | * TI (Trigger Interface): 20+1 | ||
* signal distribution module: 19+1 | * SD (signal distribution module): 19+1 | ||
* TD (trigger distr): 3+1 | |||
* SSP (Subsystem processor): 6+1 | * SSP (Subsystem processor): 6+1 | ||
* GTP (Global Trigger processor): | * Fanout (or SSP): 1 | ||
* GTP (Global Trigger processor): 2+1 | |||
* ADB backplanes: 18+1 -> $1163*19=$22097 | * ADB backplanes: 18+1 -> $1163*19=$22097 | ||
* MUX boards: 252+3 -> $741*255=$188955 | * MUX boards: 252+3 -> $741*255=$188955 | ||
* VXS crate: | * TS (trigger supervisor): 1+1 | ||
* VXS crate: 2+1 (18 crates are included into FADC system) | |||
* cables etc | |||
.... | .... | ||
Optional equipment: | Optional equipment: | ||
Line 16: | Line 20: | ||
Updated documents will be prepared by Sergey B. before July 8 workshop. | Updated documents will be prepared by Sergey B. before July 8 workshop. | ||
4 lines for FADC |
Revision as of 09:35, 1 July 2009
present:
1.СLAS12 trigger: following equipment needed for the CLAS12 trigger system:
- CTP (Crate Trigger Processor): 19+1
- TI (Trigger Interface): 20+1
- SD (signal distribution module): 19+1
- TD (trigger distr): 3+1
- SSP (Subsystem processor): 6+1
- Fanout (or SSP): 1
- GTP (Global Trigger processor): 2+1
- ADB backplanes: 18+1 -> $1163*19=$22097
- MUX boards: 252+3 -> $741*255=$188955
- TS (trigger supervisor): 1+1
- VXS crate: 2+1 (18 crates are included into FADC system)
- cables etc
.... Optional equipment:
- SFP (segment finder processor): 18+1 -> $1640*19=$31160
- RFP (road finder processor): 6+1 (can be combined with SSP - to be decided)
Updated documents will be prepared by Sergey B. before July 8 workshop.
4 lines for FADC