CLAS12 Online System: Difference between revisions
Jump to navigation
Jump to search
Line 1: | Line 1: | ||
== Disassembling schedule in the Hall == | == Disassembling schedule in the Hall == | ||
* Network wiring securing/removal, protecting/relocation of the fiber uplinks | * Network wiring securing/removal, protecting/relocation of the fiber uplinks - 6 mandays | ||
* Unused equipment removal - 10 mandays | |||
* Unused equipment removal | |||
== Assembling schedule in the Hall == | == Assembling schedule in the Hall == |
Revision as of 15:01, 19 February 2009
Disassembling schedule in the Hall
- Network wiring securing/removal, protecting/relocation of the fiber uplinks - 6 mandays
- Unused equipment removal - 10 mandays
Assembling schedule in the Hall
- Removal of the remaining cables on FC - 20 mandays
- New racks installation (two 7ft racks on FC level2, ten 6ft racks on FC level 0) - ?? mandays
- Patch panels (PMT Signals, High Voltage, Network etc) installation/relocation in racks - 10 mandays
- Crates (High Voltage, VME, VME64X, VXS, NIM, CAMAC, ADB, FASTBUS etc) installation/relocation in racks - 60 mandays
- Network equipment (Switches, Terminal Servers etc) installation in racks - 10 mandays
- Boards (ADC, TDC, High Voltage etc) installation/relocation in crates - 30 mandays
- Network wiring (interlinks by purchased cables, uplinks by contractors if necessary) - 15 mandays
- Computers replacig/installation - 10 mandays
- Preliminary testing/fixing of assembled electronics - 20 mandays
Work in Counting Room
- Replacing old equipment in convenient time, must be completed just before first run starts - 60 mandays