CLAS12 Online System: Difference between revisions

From CLONWiki
Jump to navigation Jump to search
No edit summary
Line 9: Line 9:
* Removal of the remaining cables on FC - 20 mandays
* Removal of the remaining cables on FC - 20 mandays


* New racks installation (2 7ft racks on FC level2, 10 6ft racks on FC level 0) - ?? mandays
* New racks installation (two 7ft racks on FC level2, ten 6ft racks on FC level 0) - ?? mandays


* Patch panels (PMT Signals, High Voltage, Network etc) installation/relocation in racks - 2 mandays
* Patch panels (PMT Signals, High Voltage, Network etc) installation/relocation in racks - 2 mandays

Revision as of 14:19, 19 February 2009

Disassembling schedule in the Hall

  • Network wiring securing/removal, protecting/relocation of the fiber uplinks
  • Unused equipment removal

Assembling schedule in the Hall

  • Removal of the remaining cables on FC - 20 mandays
  • New racks installation (two 7ft racks on FC level2, ten 6ft racks on FC level 0) - ?? mandays
  • Patch panels (PMT Signals, High Voltage, Network etc) installation/relocation in racks - 2 mandays
  • Crates (High Voltage, VME, VME64X, VXS, NIM, CAMAC, ADB, FASTBUS etc) installation/relocation in racks - 60 mandays
  • Network equipment (Switches, Terminal Servers etc) installation in racks - 10 mandays
  • Boards (ADC, TDC, High Voltage etc) installation/relocation in crates - 30 mandays
  • Network wiring (interlinks by purchased cables, uplinks by contractors if necessary) - 15 mandays
  • Preliminary testing/fixing of assembled electronics - 20 mandays

Work in Counting Room

  • Replacing old equipment in convenient time, must be completed just before first run starts