== Assembling schedule in the Hall == | == Assembling schedule in the Hall == | ||
* Removal of the remaining cables on FC | * Removal of the remaining cables on FC - 10 mandays | ||
* New racks installation (2 7ft racks on FC level2, 10 6ft racks on FC level 0) | * New racks installation (2 7ft racks on FC level2, 10 6ft racks on FC level 0) - ?? mandays | ||
* Patch panels (PMT Signals, High Voltage, Network etc) installation/relocation in racks | * Patch panels (PMT Signals, High Voltage, Network etc) installation/relocation in racks - 2 mandays | ||
* Crates (High Voltage, VME, VME64X, VXS, NIM, CAMAC, ADB, FASTBUS etc) installation/relocation in racks | * Crates (High Voltage, VME, VME64X, VXS, NIM, CAMAC, ADB, FASTBUS etc) installation/relocation in racks - 60 mandays | ||
* Network equipment (Switches, Terminal Servers etc) installation in racks | * Network equipment (Switches, Terminal Servers etc) installation in racks - 10 mandays | ||
* Boards (ADC, TDC, High Voltage etc) installation/relocation in crates | * Boards (ADC, TDC, High Voltage etc) installation/relocation in crates - 30 mandays | ||
* Network wiring (interlinks by purchased cables, uplinks by contractors if necessary) | * Network wiring (interlinks by purchased cables, uplinks by contractors if necessary) - 15 mandays | ||
* Preliminary testing/fixing of assembled electronics - 20 mandays | |||
== Work in Counting Room == | == Work in Counting Room == | ||
* Replacing old equipment in convenient time, must be completed just before first run starts | * Replacing old equipment in convenient time, must be completed just before first run starts |
Revision as of 14:17, 19 February 2009
Disassembling schedule in the Hall
- Network wiring securing/removal, protecting fiber uplinks
- Unused equipment removal
Assembling schedule in the Hall
- Removal of the remaining cables on FC - 10 mandays
- New racks installation (2 7ft racks on FC level2, 10 6ft racks on FC level 0) - ?? mandays
- Patch panels (PMT Signals, High Voltage, Network etc) installation/relocation in racks - 2 mandays
- Crates (High Voltage, VME, VME64X, VXS, NIM, CAMAC, ADB, FASTBUS etc) installation/relocation in racks - 60 mandays
- Network equipment (Switches, Terminal Servers etc) installation in racks - 10 mandays
- Boards (ADC, TDC, High Voltage etc) installation/relocation in crates - 30 mandays
- Network wiring (interlinks by purchased cables, uplinks by contractors if necessary) - 15 mandays
- Preliminary testing/fixing of assembled electronics - 20 mandays
Work in Counting Room
- Replacing old equipment in convenient time, must be completed just before first run starts