CLAS12 Online System: Difference between revisions
Jump to navigation
Jump to search
Line 13: | Line 13: | ||
* Patch panels (PMT Signals, High Voltage, Network etc) installation/relocation in racks | * Patch panels (PMT Signals, High Voltage, Network etc) installation/relocation in racks | ||
* Crates (High Voltage, VME, VME64X, VXS, NIM, CAMAC etc) installation/relocation in racks | * Crates (High Voltage, VME, VME64X, VXS, NIM, CAMAC, ADB, FASTBUS etc) installation/relocation in racks | ||
* | * Network equipment (Switches, Terminal Servers etc) installation in racks | ||
* Boards (ADC, TDC, High Voltage etc) installation/relocation in crates | |||
* Network wiring (interlinks by purchased cables, uplinks by contractors if necessary) |
Revision as of 14:09, 19 February 2009
Disassembling schedule
Network cables removal
Unused equipment removal
Assembling schedule
- Removal of the remaining cables on FC
- New racks installation (2 7ft racks on FC level2, 10 6ft racks on FC level 0)
- Patch panels (PMT Signals, High Voltage, Network etc) installation/relocation in racks
- Crates (High Voltage, VME, VME64X, VXS, NIM, CAMAC, ADB, FASTBUS etc) installation/relocation in racks
- Network equipment (Switches, Terminal Servers etc) installation in racks
- Boards (ADC, TDC, High Voltage etc) installation/relocation in crates
- Network wiring (interlinks by purchased cables, uplinks by contractors if necessary)