October 1, 2008 online meeting minutes: Difference between revisions
No edit summary |
No edit summary |
||
Line 1: | Line 1: | ||
present: Sergey Boyarinov | present: Sergey Boyarinov, Ben, Pawel, Valery, Sergey | ||
Line 6: | Line 6: | ||
clean AC power for dvcs racks installed, power strips installed, will be connected as first occasion | clean AC power for dvcs racks installed, power strips installed, will be connected as first occasion | ||
all discriminators connected to TDCs, all cables checked and good; | all discriminators connected to TDCs, all cables checked and good; some trigger-related 34-pair cables seems bad, will be repaired | ||
Ben prepared maps, need to incorporate them into existing map tables; DVCSTRIG firmware was modified to allow 4 reference signals into discriminators | Ben prepared maps, need to incorporate them into existing map tables (Rustam ?) ; DVCSTRIG firmware was modified to allow 4 reference signals into discriminators | ||
EC2 and CC1 fastbus crates were swapped; translation tables are adjusted | |||
new 34-pair cable was run between DVCSTRIG and CLASTRIG2 and new signal propagation measurements were conducted; results looks promising, we need to gain another 30-40 ns to be in time, one more please to look is the gate cables between clastrig2 rack and fastbus crates, they can be shorter, Chris is arranging new cables layout; forward carrage will be moved into final position soon and final measurements will be conducted then | new 34-pair cable was run between DVCSTRIG and CLASTRIG2 and new signal propagation measurements were conducted; results looks promising, we need to gain another 30-40 ns to be in time, one more please to look is the gate cables between clastrig2 rack and fastbus crates, they can be shorter, Chris is arranging new cables layout; forward carrage will be moved into final position soon and final measurements will be conducted then | ||
software: both DVCSTRIG and CLASTRIG2 GUIs are operational, more tests will be performed; Ben provided header files so we can adjust our scripts and EPICS, work is in progress | software: both DVCSTRIG and CLASTRIG2 GUIs are operational, more tests will be performed; Ben provided header files so we can adjust our scripts and EPICS, work is in progress | ||
quadrons still counts differently even with new firmware, Ben will replace v1495 board | |||
2m cables must be checked as connected, patch panels maybe moved; vme crate must be moved down | |||
Pawel is working on lookup table procedures | Pawel is working on lookup table procedures | ||
other activity discussed on previous meetings still to me conducted: need some trigger logic test; Hovanes may need to modify EPICS GUIs, Sergey B. need to fix EPICS stuff | other activity discussed on previous meetings still to me conducted: need some trigger logic test; Hovanes may need to modify EPICS GUIs, Sergey B. need to fix EPICS stuff, lookup table downloading procedures etc | ||
trigger logic test: CLAS part will be tested by Ben using lookup tables from Pawel and pattern generator; DVCS will be tested using discriminator masks, have to decide on original clusters set for both IC and Hodoscope | |||
* CLAS12 central tof test setup | * CLAS12 central tof test setup |
Revision as of 09:43, 1 October 2008
present: Sergey Boyarinov, Ben, Pawel, Valery, Sergey
- dvcs trigger
clean AC power for dvcs racks installed, power strips installed, will be connected as first occasion
all discriminators connected to TDCs, all cables checked and good; some trigger-related 34-pair cables seems bad, will be repaired
Ben prepared maps, need to incorporate them into existing map tables (Rustam ?) ; DVCSTRIG firmware was modified to allow 4 reference signals into discriminators
EC2 and CC1 fastbus crates were swapped; translation tables are adjusted
new 34-pair cable was run between DVCSTRIG and CLASTRIG2 and new signal propagation measurements were conducted; results looks promising, we need to gain another 30-40 ns to be in time, one more please to look is the gate cables between clastrig2 rack and fastbus crates, they can be shorter, Chris is arranging new cables layout; forward carrage will be moved into final position soon and final measurements will be conducted then
software: both DVCSTRIG and CLASTRIG2 GUIs are operational, more tests will be performed; Ben provided header files so we can adjust our scripts and EPICS, work is in progress
quadrons still counts differently even with new firmware, Ben will replace v1495 board
2m cables must be checked as connected, patch panels maybe moved; vme crate must be moved down
Pawel is working on lookup table procedures
other activity discussed on previous meetings still to me conducted: need some trigger logic test; Hovanes may need to modify EPICS GUIs, Sergey B. need to fix EPICS stuff, lookup table downloading procedures etc
trigger logic test: CLAS part will be tested by Ben using lookup tables from Pawel and pattern generator; DVCS will be tested using discriminator masks, have to decide on original clusters set for both IC and Hodoscope
- CLAS12 central tof test setup