present: Sergey Boyarinov,
1. G9A run status
- Lecroy 2313 discr replacements: RF (1), TOF (..)
repair status need JLAB discr: ..
- RF monitoring was improved in PAW monitoring
- Jerry built online recsis, it runs but crashes and it does not fill occupancy plots, work in progress
2. Projects review:
- CLAS12 trigger: Ben and Sergey are working
- EPICS: Lecroy HV support was implemented in 3.14 and under testing in classc0 test setup, now we have both CAENs and Lecroy HV implemented, as well as HallSystems
separate alarms will be generated for test setup (Nerses)
TO DO: use standard iocCore instead of custom ones as it is done now
- BONUS readout
PCI TI board is in progress by Ben, we have a list of equipment needed, will buy it shortly after making sure we have necessary software support
- electronics inventory db
Sergey P. is filling up database, in a meanwhile we can start to implement notification scripts, for example 'repair status' and 'spare status'
.....