Created page with "present: Sergey Boyarinov 1. FADC250 testing plan: will buy 10 fanouts $1900 each, will ask Chris to produce them ASAP, because FADC in test setups can not be used without fanou..." |
No edit summary |
||
Line 1: | Line 1: | ||
present: Sergey Boyarinov | present: Sergey Boyarinov, Sergey Pozdnyakov, Somov, Pasyuk, Egiyan | ||
1. FADC250 testing plan: will buy 10 fanouts $1900 each, will ask Chris to produce them ASAP, because FADC in test setups can not be used without fanouts; first board is in test setup, works from internal trigger but fails from external, tests just started so some results will be in a week; | 1. FADC250 testing plan: will buy 10 fanouts $1900 each, will ask Chris to produce them ASAP, because FADC in test setups can not be used without fanouts; first board is in test setup, works from internal trigger but fails from external, tests just started so some results will be in a week; | ||
2. IRMIS | 2. IRMIS |
Revision as of 09:09, 14 September 2011
present: Sergey Boyarinov, Sergey Pozdnyakov, Somov, Pasyuk, Egiyan
1. FADC250 testing plan: will buy 10 fanouts $1900 each, will ask Chris to produce them ASAP, because FADC in test setups can not be used without fanouts; first board is in test setup, works from internal trigger but fails from external, tests just started so some results will be in a week;
2. IRMIS