October 3, 2007 online meeting minutes: Difference between revisions

From CLONWiki
Jump to navigation Jump to search
Boiarino (talk | contribs)
No edit summary
Boiarino (talk | contribs)
No edit summary
Line 7: Line 7:




* PCAL
* PCAL (works, +5V fixed, signal distr board replaced, 1 sec delay introduced in 'go' to fix hunging)






* Wolfram
* Wolfram (works, ROOT too slow and will be addressed during upcoming run preparations)





Revision as of 08:59, 3 October 2007

DVCS Trigger System


Projects


  • PCAL (works, +5V fixed, signal distr board replaced, 1 sec delay introduced in 'go' to fix hunging)


  • Wolfram (works, ROOT too slow and will be addressed during upcoming run preparations)


  • Lecroy repairs, sy527 AC connectors replacement
  • PrPMC880 replacement
  • Frost preparations: all power turned on including DC FASTBUS crates, ethernet/serial cables ran for target platform;

Carl still working on ET modifications, tests to be started dayli, new version expected in about a week, we'll wait, do modifications and then run full CLAS DAQ test

TODO:

  • sy527 support (similar to sy1527 but in VME crate because of VME CAENAT board v288)
  • v1190/v1290 extensive testing (CBLT, slot#, install mv6100 in the hall and switch to 2eSST)
  • DVCS Trigger Development
  • Hall B electronics inventarization
  • Upcoming run preparations on requests (fix flip-related problem in online delay reporting correction procedure, ..)