September 12, 2007 online meeting minutes: Difference between revisions
No edit summary |
No edit summary |
||
Line 3: | Line 3: | ||
We descussed the progress in our current projects: | We descussed the progress in our current projects: | ||
1. Preshower calorimeter test setup (PCAL) was equiped with new electronics, including FASTBUS 1872 TDC board, VME camac controller installed into second SFI slot, CAMAC crate with controller, 2313 discriminator, HV SY1527 mainframe with HV board and patch panel. Softioc for HV will be running on ''clonpc3''. DAQ software was adjusted. As soon as wiring is finished we'll start testing entire system. | 1. Preshower calorimeter test setup (PCAL) was equiped with new electronics, including FASTBUS 1872 TDC board, VME camac controller installed into second SFI slot, CAMAC crate with controller, 2313 discriminator, HV SY1527 mainframe with HV board (hvec1 taken from HAll B FC) and patch panel. Softioc for HV will be running on ''clonpc3''. DAQ software was adjusted. As soon as wiring is finished we'll start testing entire system. | ||
2. | 2. CLAS TOF system upgrade is almost completed: everything installed except cables between patch panel and 1881 ADCs (they were ordered and should be here this week). We have new v1190 TDC board in sc2 crate, 7 new 2313 discriminators installed in branch 0 camac 1, new 1881 ADC board installed in slot 15 crate sc1, 2 patch panels, all necessary cabeling. Discriminator-controlling software was adjusted, ROC13.tab and ROC22.tab translation tables modified. | ||
nnn |
Revision as of 09:43, 13 September 2007
present: Sergey Boyarinov, Sergey Pozdnyakov, Stepan Stepanyan, Elliott Wolin, Mark Ito, Nerses Gevorgyan, Nikolay Balasanyan, Chris Cuevas, Benjamin Raydo
We descussed the progress in our current projects:
1. Preshower calorimeter test setup (PCAL) was equiped with new electronics, including FASTBUS 1872 TDC board, VME camac controller installed into second SFI slot, CAMAC crate with controller, 2313 discriminator, HV SY1527 mainframe with HV board (hvec1 taken from HAll B FC) and patch panel. Softioc for HV will be running on clonpc3. DAQ software was adjusted. As soon as wiring is finished we'll start testing entire system.
2. CLAS TOF system upgrade is almost completed: everything installed except cables between patch panel and 1881 ADCs (they were ordered and should be here this week). We have new v1190 TDC board in sc2 crate, 7 new 2313 discriminators installed in branch 0 camac 1, new 1881 ADC board installed in slot 15 crate sc1, 2 patch panels, all necessary cabeling. Discriminator-controlling software was adjusted, ROC13.tab and ROC22.tab translation tables modified.
nnn