May 21, 2014 online meeting minutes: Difference between revisions
Jump to navigation
Jump to search
Created page with "present: Sergey Boyarinov 1. HPS DAQ/Trigger status: 2. CLAS12 DAQ installation status:" |
No edit summary |
||
(One intermediate revision by the same user not shown) | |||
Line 1: | Line 1: | ||
present: Sergey Boyarinov | present: Sergey Boyarinov, Ben, Chris, Gu, Vlery K. | ||
1. HPS DAQ/Trigger status: | 1. HPS DAQ/Trigger status: 5G 2 lines works, 2 crates, 2 GTPs, one SSP, CODA software - all ready to run; to do: | ||
* configuration: config file to be finished - Sergey B., DiagGUI - install in github, configure servers/clients - Ben, Sergey B. | |||
* monitoring: scalers to CODA and EPICS, will talk to Hall D and Sytnik to implement it, will feed DiagGUI, EPICS and CODA; monitoring on data stream can be contributed by Valery and Andrey (they have rich test setup monitoring written using ROOT) | |||
2. CLAS12 DAQ installation status: | * making GTP sync ROCs: Ti part is ready, Ben and Gu will work together to implement GTP-TI protocol | ||
* run time database, EPICS in data stream - deal with that later | |||
* Gu is finishing SLAC-related TI firmware | |||
* playback mode needs GEANT data - by FX (adc waveform ?); can use LED system; Valery will talk to italians to make control-monitor system to test trigger | |||
2. CLAS12 DAQ installation status: 6 sectors installed (except one crate controller tdcecal6), will finalize CODA software, mode 6 test to do |
Latest revision as of 09:38, 21 May 2014
present: Sergey Boyarinov, Ben, Chris, Gu, Vlery K.
1. HPS DAQ/Trigger status: 5G 2 lines works, 2 crates, 2 GTPs, one SSP, CODA software - all ready to run; to do:
- configuration: config file to be finished - Sergey B., DiagGUI - install in github, configure servers/clients - Ben, Sergey B.
- monitoring: scalers to CODA and EPICS, will talk to Hall D and Sytnik to implement it, will feed DiagGUI, EPICS and CODA; monitoring on data stream can be contributed by Valery and Andrey (they have rich test setup monitoring written using ROOT)
- making GTP sync ROCs: Ti part is ready, Ben and Gu will work together to implement GTP-TI protocol
- run time database, EPICS in data stream - deal with that later
- Gu is finishing SLAC-related TI firmware
- playback mode needs GEANT data - by FX (adc waveform ?); can use LED system; Valery will talk to italians to make control-monitor system to test trigger
2. CLAS12 DAQ installation status: 6 sectors installed (except one crate controller tdcecal6), will finalize CODA software, mode 6 test to do