February 5, 2014 online meeting minutes: Difference between revisions
Jump to navigation
Jump to search
Created page with "present: Sergey Boyarinov, Eugene Pasyuk, Chris Cuevas, Ben Raydo 1. CLAS12 installation progress * 2. DCRB plans 3. HPS preparations" |
No edit summary |
||
(2 intermediate revisions by the same user not shown) | |||
Line 3: | Line 3: | ||
1. CLAS12 installation progress | 1. CLAS12 installation progress | ||
* | * in progress, will take another couple of month; Chris will arrange trigger fibers installation on FC, and SF will wait | ||
3. HPS preparations | 2. DCRB plans: | ||
* we are promised 400k, will build all dcrb boards and use remaining money for at least 6 VMS crates; need to do 6U version of dcrb board | |||
3. HPS preparations | |||
* hps1 and hps2 crates were installed on forward carriage with CPUs, TIs, FADCs abd SDs; Ben will put GTPs and SSP in and start developing soon; those 2 crates may be moved to alcove for actual run or stay on FC; atca crate will be on pie tower, as well as HV mainframes and LV; discr/TDCs (if used) will be on alcove together with splitters; will decide it based on cables available; will discuss it more; if alcove is used, clean power must be provided, Sergey will check with Jason; HV will be using 1520 boards, have to check and repair them; Hai and Ben will be working on new FADC firmware, we suppose to have both timing and pulse integration in trigger chain |
Latest revision as of 11:02, 5 February 2014
present: Sergey Boyarinov, Eugene Pasyuk, Chris Cuevas, Ben Raydo
1. CLAS12 installation progress
- in progress, will take another couple of month; Chris will arrange trigger fibers installation on FC, and SF will wait
2. DCRB plans:
- we are promised 400k, will build all dcrb boards and use remaining money for at least 6 VMS crates; need to do 6U version of dcrb board
3. HPS preparations
- hps1 and hps2 crates were installed on forward carriage with CPUs, TIs, FADCs abd SDs; Ben will put GTPs and SSP in and start developing soon; those 2 crates may be moved to alcove for actual run or stay on FC; atca crate will be on pie tower, as well as HV mainframes and LV; discr/TDCs (if used) will be on alcove together with splitters; will decide it based on cables available; will discuss it more; if alcove is used, clean power must be provided, Sergey will check with Jason; HV will be using 1520 boards, have to check and repair them; Hai and Ben will be working on new FADC firmware, we suppose to have both timing and pulse integration in trigger chain