CLAS12 Online System: Difference between revisions

From CLONWiki
Jump to navigation Jump to search
 
(7 intermediate revisions by the same user not shown)
Line 1: Line 1:
== Disassembling schedule in the Hall ==
== Disassembling schedule in the Hall ==


* Network wiring securing/removal, protecting/relocation of the fiber uplinks
* Network wiring securing/removal, protecting/relocation of the fiber uplinks - 6 mandays
 
* Unused equipment removal - 10 mandays
* Unused equipment removal


== Assembling schedule in the Hall ==
== Assembling schedule in the Hall ==


* Removal of the remaining cables on FC - 20 mandays
* Removal of the remaining cables on FC - 20 mandays
 
* New racks installation (two 7ft racks on FC level2, ten 6ft racks on FC level 0) - ?? mandays
* New racks installation (2 7ft racks on FC level2, 10 6ft racks on FC level 0) - ?? mandays
* Patch panels (PMT Signals, High Voltage, Network etc) installation/relocation in racks - 10 mandays
 
* Patch panels (PMT Signals, High Voltage, Network etc) installation/relocation in racks - 2 mandays
 
* Crates (High Voltage, VME, VME64X, VXS, NIM, CAMAC, ADB, FASTBUS etc) installation/relocation in racks - 60 mandays
* Crates (High Voltage, VME, VME64X, VXS, NIM, CAMAC, ADB, FASTBUS etc) installation/relocation in racks - 60 mandays
* Network equipment (Switches, Terminal Servers etc) installation in racks - 10 mandays
* Network equipment (Switches, Terminal Servers etc) installation in racks - 10 mandays
 
* Signal/Network patch panels wiring - contractors job, can be done in 5 calendar days
* Boards (ADC, TDC, High Voltage etc) installation/relocation in crates - 30 mandays
* Boards (ADC, TDC, High Voltage etc) installation/relocation in crates - 30 mandays
 
* Boards cabeling and Network wiring - 30 mandays
* Network wiring (interlinks by purchased cables, uplinks by contractors if necessary) - 15 mandays
* Computers replacing/installation - 10 mandays
 
* Preliminary testing/fixing of assembled electronics - 20 mandays
* Preliminary testing/fixing of assembled electronics - 20 mandays


== Work in Counting Room ==
== Work in Counting Room ==


* Replacing old equipment in convenient time, must be completed just before first run starts
* Replacing old equipment (any convenient time, must be completed just before first run starts) - 60 mandays

Latest revision as of 15:02, 19 February 2009

Disassembling schedule in the Hall

  • Network wiring securing/removal, protecting/relocation of the fiber uplinks - 6 mandays
  • Unused equipment removal - 10 mandays

Assembling schedule in the Hall

  • Removal of the remaining cables on FC - 20 mandays
  • New racks installation (two 7ft racks on FC level2, ten 6ft racks on FC level 0) - ?? mandays
  • Patch panels (PMT Signals, High Voltage, Network etc) installation/relocation in racks - 10 mandays
  • Crates (High Voltage, VME, VME64X, VXS, NIM, CAMAC, ADB, FASTBUS etc) installation/relocation in racks - 60 mandays
  • Network equipment (Switches, Terminal Servers etc) installation in racks - 10 mandays
  • Signal/Network patch panels wiring - contractors job, can be done in 5 calendar days
  • Boards (ADC, TDC, High Voltage etc) installation/relocation in crates - 30 mandays
  • Boards cabeling and Network wiring - 30 mandays
  • Computers replacing/installation - 10 mandays
  • Preliminary testing/fixing of assembled electronics - 20 mandays

Work in Counting Room

  • Replacing old equipment (any convenient time, must be completed just before first run starts) - 60 mandays