October 24, 2007 online meeting minutes: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
No edit summary |
||
(One intermediate revision by the same user not shown) | |||
Line 10: | Line 10: | ||
* suspicious mainframe in tagger area (PS, ST, ...) - Eugene will look at, may redistribute cards to other mainframes including new sy1527 | * suspicious mainframe in tagger area (PS, ST, ...) - Eugene will look at, may redistribute cards to other mainframes including new sy1527 | ||
'''epics''': | '''epics''': | ||
Line 21: | Line 22: | ||
* Hallsystems works for LAC, incorporated into ioc restart GUI, still need UNIX version | * Hallsystems works for LAC, incorporated into ioc restart GUI, still need UNIX version | ||
* alarm screens - works now | * alarm screens - works now in new epics, will check in and make old epics | ||
* do we need epics archiving for HV channel currents ? and voltages ? Nerses will look at that after run started | * do we need epics archiving for HV channel currents ? and voltages ? Nerses will look at that after run started | ||
* scaler gui: add target channels (Eugene, Nerses) | |||
Line 30: | Line 33: | ||
* Franz made several G9A-specific histograms | * Franz made several G9A-specific histograms | ||
* need to fix photon run particle ID part - Sergey is working (it was used to the long time to reconstruct electrons only) | * need to fix photon run particle ID part - Sergey is working (it was used to the long time to reconstruct electrons only); Eugene will help | ||
'''other''': | '''other''': | ||
* clonhp2 maintenance kit arrived bad, ordered new one | |||
* counting house cleanup was performed, exsessing in progress | * counting house cleanup was performed, exsessing in progress | ||
* Eugene is fixing EPICS variables list; cron job control needed (cdev -> ca, -9999. will be monitored) | * Eugene is fixing EPICS variables list; cron job control needed (cdev -> ca, -9999. will be monitored); see Stepan's mail (Halls energies) | ||
* expecting G9A run starting date is October 30 |
Latest revision as of 10:20, 24 October 2007
present: Sergey Boyarinov, Eugene Pasyuk, Sergey Pozdnyakov, Nerses Gevorgyan, Stepan Stepanyan
mainframes:
- one Lecroy arrived from repair, under testing in the test setup, works so far; Lei will install it instead of EC #4, which will be tested in test setup and decision will be made on possible repair
- 6-ch HV boards arrived from repair, works, installed instead of 12-ch (beam line devices)
- patch panels for new 48-ch HV boards are in progress (Armen)
- suspicious mainframe in tagger area (PS, ST, ...) - Eugene will look at, may redistribute cards to other mainframes including new sy1527
epics:
- mainframes <-> iocs table in progress, first version on web (Nerses); page on slow control for some iocs (always; he will know if post-reboot config is needed, it will be in the list)
- Nerses if making preparations in epics to switch to the sy1527 from Lecroy if needed
- some problems were observed related to the bigsubRecord implementation, works now but need to be understood
- Hallsystems works for LAC, incorporated into ioc restart GUI, still need UNIX version
- alarm screens - works now in new epics, will check in and make old epics
- do we need epics archiving for HV channel currents ? and voltages ? Nerses will look at that after run started
- scaler gui: add target channels (Eugene, Nerses)
fast reconstruction:
- Franz made several G9A-specific histograms
- need to fix photon run particle ID part - Sergey is working (it was used to the long time to reconstruct electrons only); Eugene will help
other:
- clonhp2 maintenance kit arrived bad, ordered new one
- counting house cleanup was performed, exsessing in progress
- Eugene is fixing EPICS variables list; cron job control needed (cdev -> ca, -9999. will be monitored); see Stepan's mail (Halls energies)
- expecting G9A run starting date is October 30