October 3, 2007 online meeting minutes: Difference between revisions
No edit summary |
No edit summary |
||
(4 intermediate revisions by the same user not shown) | |||
Line 3: | Line 3: | ||
'''DVCS Trigger System''' | '''DVCS Trigger System''' | ||
Ben presented preliminary [http://clonweb/wiki/clondocs/DVCS_Trigger/PreliminaryDesign.ppt design] of the system. It based on v1495 boards equiped with A395A and A395D cards. System uses 200MHz clock wich 4-clock data processing cycles. There is no external start, system works as pipeline. In according to Stepan time difference between hits in the same cluster is smaller then few ns, so with processing clock 50MHz we will set discriminator's output signals to about 30ns to | Ben presented preliminary [http://clonweb/wiki/clondocs/DVCS_Trigger/PreliminaryDesign.ppt design] of the system. It based on v1495 boards equiped with A395A and A395D cards. System uses 200MHz clock wich 4-clock data processing cycles. There is no external start, system works as pipeline. In according to Stepan time difference between hits in the same cluster is smaller then few ns, so with processing clock 50MHz we will set discriminator's output signals to about 30ns to enforce coinsidence. Preliminary Ben estimated that 8-9 cycles at 50MHz will be needed for the system to make the decision. | ||
Ben will continue with system simulation and i/o performance testing. We will prepare DVCS data file which can be used in simulation process. In about one month we'll make a final decision on hardware and order it. Preliminary, if current design will be used, we'll need following boards (with spares): v1495 (6 units), A395A (11 units), A395D (2 units). We may be able to borrow v1495 from other JLAB groups to speedup developing. | |||
'''Projects''' | |||
* PCAL test setup finally works: +5V fixed, signal distribution board replaced, 1 sec delay introduced in 'go' transition to fix hunging on the first event (must understand that !). Stepan asked about 10 times better ADC resolution: one of the options can be 2+ Gsample PCI card, but TI board in PCI format is needed. Need to ask Ed how that project is going. | |||
* Active collimator probably needed in DAQ, will be discussed when decision will be made. | |||
* Wolfram test setup works, ROOT too slow when attached to the ET system and holds data flow, it will be addressed during upcoming run preparations (select function, control word bit by EB ???). | |||
* For Lecroy mainframes were sent to be repaired. | |||
* | * sy527 AC connectors arrived, we'll arrange replacement | ||
* Motorola seems agree to replace unrepairable PrPMC880 with equivalent board (newer version of PMC280), hopefully we can use it | |||
* Frost preparations: all power turned on including DC FASTBUS crates, ethernet/serial cables ran for target platform; Carl still working on ET modifications, tests to be started shortly, new version expected in about a week, we'll wait for the final version, do modifications and then run full CLAS DAQ test; new EPICS channels from target maybe needed in data stream, and some of existing channels proably renaimed, need check | |||
* Frost preparations: all power turned on including DC FASTBUS crates, ethernet/serial cables ran for target platform; | |||
Carl still working on ET modifications, tests to be started | |||
modifications and then run full CLAS DAQ test; new EPICS channels from target | |||
TODO: | TODO: | ||
* sy1527: reboot button | * sy1527 in epics: add reboot button into standard IOC reboot menu; reconnect is not implemented after hardware reboot, must be addressed | ||
* | * sy527 in epics: Sergey B. is working on it, will be done similar to sy1527's support but in vxWorks; it will run in VME crate because of VME v288 CAENET controller is used to talk to sy527 mainframes; first application will be LAC HV system; if successful, can be used for DC in parallel with DCHV program; those efforts is part of our monitoring system development: as we discussed before all information will be presented as EPICS CA to be available to higher level monitoring components | ||
* | * v1190/v1290 extensive testing with new firmware: CBLT and slot# problems will be investigated; install mv6100 in the hall, switch to 2eSST and run tests | ||
* Hall B electronics | * Hall B electronics inventory - Sergey P. is working on it | ||
* Upcoming run preparations on requests (fix flip-related problem in online delay reporting correction procedure, ..) | * Upcoming run preparations on requests (fix flip-related problem in online delay reporting correction procedure, ..) | ||
* beam test with preshower during upcoming run - will | * beam test with preshower during upcoming run - Stepan will present it on one of the future meetings | ||
* | * Hall D test may be conducted in Hall B some time next summer; since electronic pool does not exist people should think about equipment in advance |
Latest revision as of 21:42, 9 October 2007
present: Sergey Boyarinov, Sergey Pozdnyakov, Nerses Gevorgyan, Tanest Chinwanawich, Elliott Wolin, Benjamin Raydo, Stepan Stepanyan
DVCS Trigger System
Ben presented preliminary design of the system. It based on v1495 boards equiped with A395A and A395D cards. System uses 200MHz clock wich 4-clock data processing cycles. There is no external start, system works as pipeline. In according to Stepan time difference between hits in the same cluster is smaller then few ns, so with processing clock 50MHz we will set discriminator's output signals to about 30ns to enforce coinsidence. Preliminary Ben estimated that 8-9 cycles at 50MHz will be needed for the system to make the decision.
Ben will continue with system simulation and i/o performance testing. We will prepare DVCS data file which can be used in simulation process. In about one month we'll make a final decision on hardware and order it. Preliminary, if current design will be used, we'll need following boards (with spares): v1495 (6 units), A395A (11 units), A395D (2 units). We may be able to borrow v1495 from other JLAB groups to speedup developing.
Projects
- PCAL test setup finally works: +5V fixed, signal distribution board replaced, 1 sec delay introduced in 'go' transition to fix hunging on the first event (must understand that !). Stepan asked about 10 times better ADC resolution: one of the options can be 2+ Gsample PCI card, but TI board in PCI format is needed. Need to ask Ed how that project is going.
- Active collimator probably needed in DAQ, will be discussed when decision will be made.
- Wolfram test setup works, ROOT too slow when attached to the ET system and holds data flow, it will be addressed during upcoming run preparations (select function, control word bit by EB ???).
- For Lecroy mainframes were sent to be repaired.
- sy527 AC connectors arrived, we'll arrange replacement
- Motorola seems agree to replace unrepairable PrPMC880 with equivalent board (newer version of PMC280), hopefully we can use it
- Frost preparations: all power turned on including DC FASTBUS crates, ethernet/serial cables ran for target platform; Carl still working on ET modifications, tests to be started shortly, new version expected in about a week, we'll wait for the final version, do modifications and then run full CLAS DAQ test; new EPICS channels from target maybe needed in data stream, and some of existing channels proably renaimed, need check
TODO:
- sy1527 in epics: add reboot button into standard IOC reboot menu; reconnect is not implemented after hardware reboot, must be addressed
- sy527 in epics: Sergey B. is working on it, will be done similar to sy1527's support but in vxWorks; it will run in VME crate because of VME v288 CAENET controller is used to talk to sy527 mainframes; first application will be LAC HV system; if successful, can be used for DC in parallel with DCHV program; those efforts is part of our monitoring system development: as we discussed before all information will be presented as EPICS CA to be available to higher level monitoring components
- v1190/v1290 extensive testing with new firmware: CBLT and slot# problems will be investigated; install mv6100 in the hall, switch to 2eSST and run tests
- Hall B electronics inventory - Sergey P. is working on it
- Upcoming run preparations on requests (fix flip-related problem in online delay reporting correction procedure, ..)
- beam test with preshower during upcoming run - Stepan will present it on one of the future meetings
- Hall D test may be conducted in Hall B some time next summer; since electronic pool does not exist people should think about equipment in advance