April 24, 2019 online meeting minutes: Difference between revisions
Jump to navigation
Jump to search
Created page with "present: Sergey Boyarinov, 1. HallB cosmic runs organization 2. HPS preparations * DAQ status * TIpcie board integration with SVT * trigger status * installation and..." |
No edit summary |
||
(One intermediate revision by the same user not shown) | |||
Line 1: | Line 1: | ||
present: Sergey Boyarinov, | present: Sergey Boyarinov, Stepan Stepanyan, Graham, vpk, Rafo, Nathan, Ben | ||
1. HallB cosmic runs organization | 1. HallB cosmic runs organization: svt test setup can work now with and without ts, all wiring is done, Yuri will check data consistency; in general we can run our major sets in parallel | ||
2. HPS preparations | 2. HPS preparations | ||
* DAQ status | * DAQ status: cleanup, new release will be made; daq is running in the hall with 3 vie crates and 2 servers, everything is ready, waiting for ECAL and SVT | ||
* TIpcie board integration with SVT: test setup in SLAC is operational, SVT electronics being prepared there, some issues still exist, in particular phase synchronization have to be worked out | |||
* trigger status: by the end of week Ben will finish trigger simulation and will be ready for commissioning; all triggers presented in January in SLAC will be implemented, actual production and calibration triggers will be discussed | |||
* installation and commissioning plans: ECAL will be on Monday April 29, 2 scintillators are ready and will be installed as well, then trigger tests can be started; we have to finish in one week before SVT arrives May 6; if trigger delayed SD outputs can be used; SVT installation and testing will take about 10 days | |||
* | * HPS run starts Monday June 17; MCC starts June 10 so we may be ready few days before just in case; will go until August 18 | ||
* | * Nathan will look at HPS slow control if it can/should be merged with CLAS | ||
* | * utility power will be added in alcove |
Latest revision as of 09:35, 24 April 2019
present: Sergey Boyarinov, Stepan Stepanyan, Graham, vpk, Rafo, Nathan, Ben
1. HallB cosmic runs organization: svt test setup can work now with and without ts, all wiring is done, Yuri will check data consistency; in general we can run our major sets in parallel
2. HPS preparations
- DAQ status: cleanup, new release will be made; daq is running in the hall with 3 vie crates and 2 servers, everything is ready, waiting for ECAL and SVT
- TIpcie board integration with SVT: test setup in SLAC is operational, SVT electronics being prepared there, some issues still exist, in particular phase synchronization have to be worked out
- trigger status: by the end of week Ben will finish trigger simulation and will be ready for commissioning; all triggers presented in January in SLAC will be implemented, actual production and calibration triggers will be discussed
- installation and commissioning plans: ECAL will be on Monday April 29, 2 scintillators are ready and will be installed as well, then trigger tests can be started; we have to finish in one week before SVT arrives May 6; if trigger delayed SD outputs can be used; SVT installation and testing will take about 10 days
- HPS run starts Monday June 17; MCC starts June 10 so we may be ready few days before just in case; will go until August 18
- Nathan will look at HPS slow control if it can/should be merged with CLAS
- utility power will be added in alcove