September 26, 2012 online meeting minutes: Difference between revisions
No edit summary |
No edit summary |
||
(3 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
present: Sergey Boyarinov, Sergey Pozdnyakov, FX | present: Sergey Boyarinov, Sergey Pozdnyakov, FX | ||
1. Inventory: | 1. Inventory: Sergey B. 'almost' finished cables implementation to the inventory, following problems were observed during demonstration: | ||
* problem observed when connector's 'saveAsNew' pushed, if it was no connectors | |||
* Drop 'id' from item list and cable list, and quantity in item list | |||
* connector name and connector type must be in different columns in cable list | |||
* Add after 'brands' on 3rd line: 'cable types' and 'connector types' | |||
* 'show cables without connectors' checkbox must be checked on first entry | |||
* Add group operations to the cables | |||
* Picture's show button or similar to display pictures | |||
* Always sorting connectors by name | |||
Dan Carman requested to speedup cable labeling decision, will do it promptly. | |||
2. CLAS12 construction: we received last 3 sy4527 mainframes, they were moved to the FC level2 but not installed yet | Need simple cable label machine. | ||
2. CLAS12 construction: we received last 3 sy4527 mainframes, they were moved to the FC level2 but not installed yet. We have 12 mainframes total, may need couple more. Still need to calculate available HV patch panels and decide how many special tof patch panels do we need (and cable length); sy1535 boards testing under way, will be done in about 1 week; to start HV installation we need: identify exact locations, restore floot panels on FC level2 and level3, relocate VESDA pipes and install racks on FC level1(including assembling and fastening them to the floor and to each other), run electrical on FC level1. We also need to install 2 more racks on FC level3 (cab take them from tage area - former DVCS HV and HPS HV), and it must be done before shields start running cables (in 2 weeks). After that VXS and VME crates installation can be started. UPSes still need to be wired to the emergency generators. |
Latest revision as of 12:45, 26 September 2012
present: Sergey Boyarinov, Sergey Pozdnyakov, FX
1. Inventory: Sergey B. 'almost' finished cables implementation to the inventory, following problems were observed during demonstration:
- problem observed when connector's 'saveAsNew' pushed, if it was no connectors
- Drop 'id' from item list and cable list, and quantity in item list
- connector name and connector type must be in different columns in cable list
- Add after 'brands' on 3rd line: 'cable types' and 'connector types'
- 'show cables without connectors' checkbox must be checked on first entry
- Add group operations to the cables
- Picture's show button or similar to display pictures
- Always sorting connectors by name
Dan Carman requested to speedup cable labeling decision, will do it promptly.
Need simple cable label machine.
2. CLAS12 construction: we received last 3 sy4527 mainframes, they were moved to the FC level2 but not installed yet. We have 12 mainframes total, may need couple more. Still need to calculate available HV patch panels and decide how many special tof patch panels do we need (and cable length); sy1535 boards testing under way, will be done in about 1 week; to start HV installation we need: identify exact locations, restore floot panels on FC level2 and level3, relocate VESDA pipes and install racks on FC level1(including assembling and fastening them to the floor and to each other), run electrical on FC level1. We also need to install 2 more racks on FC level3 (cab take them from tage area - former DVCS HV and HPS HV), and it must be done before shields start running cables (in 2 weeks). After that VXS and VME crates installation can be started. UPSes still need to be wired to the emergency generators.