present: Sergey Boyarinov, Sergey Pozdnyakov
1. g14b: run started week ago, following problems were fixed:
- level2 cables connected under the CLAS
- several above-FASTBUS fans replaced, will continue
- several CPUs replaced because of PMC failures
- rate was 4 kHz at 85% livetime at 20nA beam current BEFORE level2 fixes, expecting improvements
- remaining problems