July 1, 2009 online meeting minutes: Difference between revisions

From CLONWiki
Jump to navigation Jump to search
Boiarino (talk | contribs)
No edit summary
Boiarino (talk | contribs)
No edit summary
 
(7 intermediate revisions by the same user not shown)
Line 1: Line 1:
present:  
present: Sergey Boyarinov, Sergey Pozdnyakov, Chris Cuevas, Stepan Stepanyan


1.СLAS12 trigger: following equipment needed for the CLAS12 trigger system:
1.СLAS12 trigger: following equipment needed for the CLAS12 trigger system:
* CTP (Crate Trigger Processor): 19+1
* CTP (Crate Trigger Processor): 19+1
* TI (Trigger Interface): 19+1
* TI (Trigger Interface): 20+1
* signal distribution module: 19+1
* SD (signal distribution module): 19+1
* TD (trigger distr): 3+1
* SSP (Subsystem processor): 6+1
* SSP (Subsystem processor): 6+1
* GTP (Global Trigger processor): 1+1
* Fanout (or SSP): 1
* GTP (Global Trigger processor): 2+1
* ADB backplanes: 18+1 -> $1163*19=$22097
* ADB backplanes: 18+1 -> $1163*19=$22097
* MUX boards: 252+3 -> $741*255=$188955
* MUX boards: 252+3 -> $741*255=$188955
* VXS crate: 1+1 (18 crates are included into FADC system)
* TS (trigger supervisor): 1+1
....
* VXS crate: 2+1 (18 crates are included into FADC system)
* cables etc
 
Optional equipment:
Optional equipment:
* SFP (segment finder processor): 18+1 -> $1640*19=$31160
* SFP (segment finder processor): 18+1 -> $1640*19=$31160
Line 16: Line 20:


Updated documents will be prepared by Sergey B. before July 8 workshop.
Updated documents will be prepared by Sergey B. before July 8 workshop.
4 lines for FADC
2. BONUS preparations:
* TI board is under testing, 87% live for 2kHz empty readout, need to improve, Sergey does time profiling
* BONUS card need to be tested, will ask Dave Abbott to help
3. Inventory database: need coordinates (position from top and size in inches and U-s, input with options in/u, db record like 10U or 10I); main page search does descriptions only, need to search all fields
4. HV: need to push CAEN with A1535 fixes

Latest revision as of 10:07, 1 July 2009

present: Sergey Boyarinov, Sergey Pozdnyakov, Chris Cuevas, Stepan Stepanyan

1.СLAS12 trigger: following equipment needed for the CLAS12 trigger system:

  • CTP (Crate Trigger Processor): 19+1
  • TI (Trigger Interface): 20+1
  • SD (signal distribution module): 19+1
  • TD (trigger distr): 3+1
  • SSP (Subsystem processor): 6+1
  • Fanout (or SSP): 1
  • GTP (Global Trigger processor): 2+1
  • ADB backplanes: 18+1 -> $1163*19=$22097
  • MUX boards: 252+3 -> $741*255=$188955
  • TS (trigger supervisor): 1+1
  • VXS crate: 2+1 (18 crates are included into FADC system)
  • cables etc

Optional equipment:

  • SFP (segment finder processor): 18+1 -> $1640*19=$31160
  • RFP (road finder processor): 6+1 (can be combined with SSP - to be decided)

Updated documents will be prepared by Sergey B. before July 8 workshop.

4 lines for FADC

2. BONUS preparations:

  • TI board is under testing, 87% live for 2kHz empty readout, need to improve, Sergey does time profiling
  • BONUS card need to be tested, will ask Dave Abbott to help

3. Inventory database: need coordinates (position from top and size in inches and U-s, input with options in/u, db record like 10U or 10I); main page search does descriptions only, need to search all fields

4. HV: need to push CAEN with A1535 fixes