October 24, 2007 online meeting minutes: Difference between revisions

From CLONWiki
Jump to navigation Jump to search
Boiarino (talk | contribs)
No edit summary
Boiarino (talk | contribs)
No edit summary
 
(5 intermediate revisions by the same user not shown)
Line 1: Line 1:
present: Sergey Boyarinov, Eugene Pasyuk, Sergey Pozdnyakov
present: Sergey Boyarinov, Eugene Pasyuk, Sergey Pozdnyakov, Nerses Gevorgyan, Stepan Stepanyan


'''mainframes''':
'''mainframes''':
Line 6: Line 6:


* 6-ch HV boards arrived from repair, works, installed instead of 12-ch (beam line devices)
* 6-ch HV boards arrived from repair, works, installed instead of 12-ch (beam line devices)
* patch panels for new 48-ch HV boards are in progress (Armen)
* suspicious mainframe in tagger area (PS, ST, ...) - Eugene will look at, may redistribute cards to other mainframes including new sy1527




'''epics''':
'''epics''':
* mainframes <-> iocs table in progress, first version on web (Nerses); page on slow control for some iocs (always; he will know if post-reboot config is needed, it will be in the list)


* Nerses if making preparations in epics to switch to the sy1527 from Lecroy if needed
* Nerses if making preparations in epics to switch to the sy1527 from Lecroy if needed
Line 16: Line 22:
* Hallsystems works for LAC, incorporated into ioc restart GUI, still need UNIX version
* Hallsystems works for LAC, incorporated into ioc restart GUI, still need UNIX version


* alarm screens - works now ?
* alarm screens - works now in new epics, will check in and make old epics
 
* do we need epics archiving for HV channel currents ? and voltages ? Nerses will look at that after run started
 
* scaler gui: add target channels (Eugene, Nerses)




Line 23: Line 33:
* Franz made several G9A-specific histograms
* Franz made several G9A-specific histograms


* need to fix photon run particle ID part - Sergey is working (it was used to the long time to reconstruct electrons only)
* need to fix photon run particle ID part - Sergey is working (it was used to the long time to reconstruct electrons only); Eugene will help




'''other''':
'''other''':
* clonhp2 maintenance kit arrived bad, ordered new one


* counting house cleanup was performed, exsessing in progress
* counting house cleanup was performed, exsessing in progress


* Eugene is fixing EPICS variables list; cron job control needed (cdev -> ca, -9999. will be monitored)
* Eugene is fixing EPICS variables list; cron job control needed (cdev -> ca, -9999. will be monitored); see Stepan's mail (Halls energies)
 
* expecting G9A run starting date is October 30

Latest revision as of 10:20, 24 October 2007

present: Sergey Boyarinov, Eugene Pasyuk, Sergey Pozdnyakov, Nerses Gevorgyan, Stepan Stepanyan

mainframes:

  • one Lecroy arrived from repair, under testing in the test setup, works so far; Lei will install it instead of EC #4, which will be tested in test setup and decision will be made on possible repair
  • 6-ch HV boards arrived from repair, works, installed instead of 12-ch (beam line devices)
  • patch panels for new 48-ch HV boards are in progress (Armen)
  • suspicious mainframe in tagger area (PS, ST, ...) - Eugene will look at, may redistribute cards to other mainframes including new sy1527


epics:

  • mainframes <-> iocs table in progress, first version on web (Nerses); page on slow control for some iocs (always; he will know if post-reboot config is needed, it will be in the list)
  • Nerses if making preparations in epics to switch to the sy1527 from Lecroy if needed
  • some problems were observed related to the bigsubRecord implementation, works now but need to be understood
  • Hallsystems works for LAC, incorporated into ioc restart GUI, still need UNIX version
  • alarm screens - works now in new epics, will check in and make old epics
  • do we need epics archiving for HV channel currents ? and voltages ? Nerses will look at that after run started
  • scaler gui: add target channels (Eugene, Nerses)


fast reconstruction:

  • Franz made several G9A-specific histograms
  • need to fix photon run particle ID part - Sergey is working (it was used to the long time to reconstruct electrons only); Eugene will help


other:

  • clonhp2 maintenance kit arrived bad, ordered new one
  • counting house cleanup was performed, exsessing in progress
  • Eugene is fixing EPICS variables list; cron job control needed (cdev -> ca, -9999. will be monitored); see Stepan's mail (Halls energies)
  • expecting G9A run starting date is October 30