Trigger System (CLAS12 project)
¥
¥      a) Trigger System Conceptual design (physics level)
¥  manpower: scientist
¥  duration: 3 month
¥  predecessors: none
¥  work description: evaluate current Trigger System and its limitations; make a list of new components which can improve a trigger system; present the list of proposed components as a combination of level1 and level2 subsystems communicating to each other; include both existing and proposed detectors into the system; consider good electron identification as primary goal for entire Trigger System
¥
¥     b) Trigger System simulation, Level 1 (physics level)
¥  manpower: scientist
¥  duration: 3 month
¥  predecessors: (a)
¥  work description: study the efficiency of proposed components based on CLAS data analysis for existing detectors and simulation results for proposed CLAS12 detectors (if available); the list of components must include cluster finding in calorimeters and matching between different detectors incorporated into Level 1 trigger logic; fixed execution time must be provided for any trigger component; make final list of components which should be included into CLAS12 Level 1 trigger system