Online Monitoring System upgrade
             (CLAS project)
     a) Standardization of physical components information
  manpower: scientist(s)
  duration: 6 month
  predecessors: none
  work description: in cooperation with CLAS detector groups, summarize all previous troubleshooting
       experience for every CLAS detector; make a list of EPICS CA records sufficient to deliver all
       necessary monitoring information, enforcing convenient channel naming scheme; implement
       data quality controlling IOC, as well as any other IOCs required to deliver all necessary information;
       implement monitoring functions only, but make sure it will be easy to add controlling functions in future;
       perform extensive test to check IOCs reliability and performance
¥
     b) Logic diagrams development
  manpower: scientist(s)
  duration: 3 month
  predecessors: none
  work description: develop logic diagrams necessary to describe all possible situations in CLAS detector
       operation: production data taking, calibration runs, DAQ test runs, troubleshooting, recovery etc;
       two-level concept shown on following figure should be used as guideline but final scheme can be
       different; consult with CLAS detector groups to make sure all possible situations are covered; both
       monitoring and control logic must be developed; final diagrams can be presented in any appropriate
       form