a) Standardization of
physical components information
manpower: scientist(s)
duration: 6 month
predecessors: none
work description: in cooperation with
CLAS detector groups, summarize all previous troubleshooting
experience
for every CLAS detector; make a list of EPICS CA records sufficient to deliver
all
necessary
monitoring information, enforcing convenient channel naming scheme;
implement
data
quality controlling IOC, as well as any other IOCs required to deliver all
necessary information;
implement
monitoring functions only, but make sure it will be easy to add
controlling functions in future;
perform extensive test to check IOCs
reliability and performance
¥
b) Logic diagrams
development
manpower: scientist(s)
duration: 3 month
predecessors: none
work description: develop logic
diagrams necessary to describe all possible situations in CLAS detector
operation: production data taking, calibration runs, DAQ test runs,
troubleshooting, recovery etc;
two-level
concept shown on following figure should be used as guideline but final scheme
can be
different;
consult with CLAS detector groups to make sure all possible situations are
covered; both
monitoring and control logic must be developed; final
diagrams can be presented in any appropriate
form