Project timeline (CAEN TDCs)
¥Decision to replace FASTBUS 1872/1875 boards: July 2002
¥Overall design, TDC market studies, sample boards testing: summer 2002-summer 2003
¥Requisitions for TDCs: July 2003
¥Software development: 2002-2004
¥VME64X crates installation: November 2003
¥Project rescheduled to meet EG3 run demands; completion date set to November 2004: January 2004
¥First two TDCs received and tested: February 2004
¥TDCs complete delivery: March 2004
¥TDCs test setup studies: April-June 2004
¥TDCs installation started: July 2004
¥TDCs system full assembly: September 2004
¥TDCs calibration: October-November 2004
¥TDCs system is operational: November 2004
¥TDCs used in real run (EG3): starting November 25, 2004