Project timeline (F1TDCs)
¥Decision to use F1TDCs for Time-Of-Flight system: July 2003
¥Requisition: September 2003
¥Software development: 2003-2004
¥Project rescheduled to meet EG3 run demands; completion date set to November 2004: January 2004
¥First 5 boards and temporary distribution board delivery: July 2004
¥Decision to use F1TDCs not in Time-Of-Flight system but in Large Angle Calorimeter because of lack of time: October 2004
¥Full delivery including signal distribution boards: Nov 17, 2004
¥System is working  in test setup: Nov 24, 2004
¥Project postponed because of EG3 run started Nov 25; work was resumed after EG3
¥System is operational, all boards are installed in Large Angle Calorimeter in low resolution mode: March 2005
¥TDCs used in real run (DVCS): starting March 23, 2005